DPW Press Release 5/16 – Walkable Olean Phase III

PRESS RELEASE
CITY OF OLEAN

WALKABLE OLEAN PHASE III

Construction continues on Walkable Olean Phase III along East State Street from Front Street to North Union Street.

Work is scheduled as follows:

  • Bike lane markings along sidewalk trail on Monday, May 19th
  • Milling of E State Street from North Union Street to East Avenue on Wednesday, May 21st
  • Paving of E State Street from North Union Street to East Avenue on Thursday, May 22nd and Friday May  23rd
  • Striping of East State Street from Monday, May 27th through Friday, May 30th  

It is recommended that motorists find alternate routes when available due to significant traffic delays expected.  We appreciate your patience as we undertake this project.

Please go to www.cityofolean.org for further details on the project.